Services

Cost & Schedule Risk Analysis (CSRA)

  1. Home
  2. Services
  3. Cost Engineering
  4. Cost schedule risk analysis csra

Answer Your Key Questions

  • How likely is my project to come in on-time and on-budget?
  • What are the chances of significant cost overrun or schedule slip?
  • How much contingency is needed to achieve the desired level of predictability?
  • What are the project risks and what is driving them? What can be done to reduce the risks?
  • How much additional time and/or money is needed for risk reduction, and is it worth it?
Let's Get Started

Talk to IPA to find out if your next project will come in on-time and on-budget.

Internal photo of a pharmaceuticals production facility.

Support Investment Decision Making

Internal photo of a pharmaceuticals production facility.

Read how a pharmaceutical company used the CSRA to evaluate cost and schedule risks for a megaproject.

Read more
Cost & Schedule Risk Anaylsis (CSRA)

Current State and Opportunities

Cost & Schedule Risk Anaylsis (CSRA)

There is significant variability in the level of maturity across owner companies in terms of implementation of cost and schedule risk analysis Best Practices.

Read more

Overview

Independent Project Analysis, Inc. (IPA) data show that the chances of a significant cost overrun or schedule slip are often higher than shown in the risk analysis supporting the Final Investment Decision (FID). Less than 45 percent of projects actually end up within +/-10 percent of their cost estimate at authorization. Additionally, the average capital project in IPA’s database slips its execution schedule by 26 percent.

IPA has developed the Cost and Schedule Risk Analysis (CSRA) to support investment decision-making by delivering unbiased and informed cost and schedule insights at this critical point in the project life cycle.

The CSRA leverages detailed data from more than 20,000 global capital projects. These data feed into IPA’s empirically proven methodology to quantify how likely a project is to meet its targets, while also identifying the potential risks and how to reduce them. By producing a true, independent picture of the project’s cost and schedule, the CSRA gives management the information and the confidence needed to make informed decisions.

Key Features & Benefits

Proven Risk Quantification Method Based on Detailed Project Data

  • Incorporate cost and schedule probability distributions into
    decision-making
  • Identify the contingency requirements to achieve a desired level of confidence that cost or schedule estimates will not overrun
  • Understand the competitiveness of the base cost and
    schedule estimates

Unbiased Data and Insights

  • Facilitate fact-based discussions between the project team and management on project risks and how to address them
  • Gain alignment between management and the project team on realistic cost and schedule estimates for an approved scope of work
  • Use real data distributions from IPA databases to inform Monte Carlo simulations and improve forecast accuracy

Comprehensive Risk Identification at the Project and System Levels

  • Explore trade-offs between risk reduction activities and the additional time and money required to implement them
  • Understand the basis for developing risk mitigation strategies
  • Develop predictable cost and schedule outcomes

Timing and Perspective

The CSRA can be used at any time during the project development phase, or the front-end, of a project. It is typically used before a stage gate—after the base estimates are complete—to enable risk quantification, cost and schedule probability curves development, and contingency requirements identification. A CSRA can also be used early in an FEL phase to identify risks and to explore different risk mitigation strategies. An early CSRA can also be used for cost and schedule target setting.

Application

The CSRA is completed through a series of stakeholder interviews, team surveys, and risk workshops, to gather information and share analysis results as they are completed. The high level of interaction enables IPA to understand the project and gain alignment with the project team on the analysis results well before the final report is completed. The process also creates opportunities for IPA to share unrivaled project research to address specific challenges the team may be facing.

Industrial Sectors

The CSRA is available to owner firms across industrial sectors. Key sectors include, but are not limited to:

  • Airports
  • Chemicals
  • Energy (Oil, Gas, Power & Renewables)
  • Food & Consumer Products
  • Hydrocarbon Processing & Transportation
  • Infrastructure
  • Life Sciences
  • Mining, Minerals & Metals
  • Nuclear
  • Pipelines
  • Pulp & Paper

Key contact

View Shubham Galav’s profile

Shubham Galav

Deputy Director, Project Research Division, Cost Group

Let's get started

Talk to IPA to find out if your next project will come in on-time and on-budget.